CIOB president Paul Nash: Industry must act on Edinburgh schools

CIOB president Paul Nash says industry cannot afford to ignore the issues raised in the Edinburgh schools report.

Paul Nash

Professor John Coles’ report into the building defects that led to emergency closure of 17 schools in Edinburgh in 2016 makes sobering reading for anyone who cares about our industry and the reputation of those who work in it.

The report lays bare the failings of those responsible for the construction of these buildings as well as the potential consequences that could have resulted were it not for “a matter of timing and luck”.

Poor-quality bricklaying, inadequate supervision and “fundamental and widespread failures of the quality assurance processes” all contributed to the eventual failure.

In fact, so serious is this case that SCOSS (Standing Committee on Structural Safety) has published an alert to highlight the structural safety implications of the report.

So how could those responsible have got it so wrong?

In its submission to the investigation, the Royal Incorporation of Architects in Scotland (RIAS) highlighted the use of design and build and what they believe is the lack of independent scrutiny that results from using this form of procurement. In my experience, design and build itself is not synonymous with a lack of quality or quality control. It is probably the most common form of procurement used today and defects on this scale are rare.

I think that we have to look beyond the procurement process and understand the behaviours that led to an acceptance of poor workmanship on these sites. This was not a single defect affecting one building, this was multiple defects that occurred on a number of projects, procured and constructed as part of a single programme of works. The only conclusion that one can draw from this is that the failing was a systemic one, which is a point that bears closer examination.

"We have to look beyond the procurement process and understand the behaviours that led to an acceptance of poor workmanship."

Paul Nash, CIOB president

Much of the industry reporting of this case has focused on the failings at trade and supervisory level. But there are many unanswered questions about the role of those responsible for commissioning, directing and managing these projects, which have wider implications for our industry and society.

And the report comes at a time when the issue of quality in construction has been making the headlines for other reasons. Recently Bovis Homes announced that it was setting aside £7m to compensate buyers for defects in new homes, recognising that their production processes were “not sufficiently robust in order to deliver the quality of homes to our customers when we would expect to deliver them”.

In other words, quality was being sacrificed for speed of delivery. For Bovis the immediate impact of failing to manage quality was on the bottom line, although the damage to its reputation is arguably greater.

Elsewhere, the investigation into the fire at Lakanal House highlighted that defective workmanship and a lack of quality control can have much more serious consequences. In this case, a lack of adequate fire protection was found to have contributed to the rapid spread of the fire that resulted in the deaths of six people. And this at the same time that the report into the Edinburgh schools identified that there was a lack of adequate fire stopping, which would have made the buildings unsafe in the event of a fire.

As professionals we have a duty to the industry and wider society to act responsibly and ethically. This defines what it means to be a professional. And we all have a responsibility for the reputation of our industry and the wellbeing of those who work within it. 

It is important that we understand the issues that allowed these defects to occur and act to ensure that it does not happen again. To this end the CIOB will be reaching out to the other professional bodies and industry representatives to create a forum to discuss the issue of quality in our industry and the steps that we need to take to improve it.

Comments

Commissioning on many of these building types tend to focus on the function and operational aspects of the building services and less on the actual structure and fabric of the building itself. Perhaps introducing structural assessment along with the construction quality reports within the commissioning scope would provide additional checks in addition to those normally specified.

Another avenue worth exploring is the quality of the design drawings and documentation provided as the preparation of such has deteriorated in terms of clarity, organisation, legibility and conciseness over the last 20 years.
Quality draughtsmanship is not taught anymore which undoubtedly impacts the interpretation and legibility of the design.

  • 21st Mar 2017, at 11:51 PM
  • Hugh

I worked on two PFI/PPP Schools Projects delivering five large secondary schools (pupil age 11 - 18). My role on both projects involved providing the "Provider" oversight of the delivery of the construction works. On this I worked closely with both the Building Contractor and the ultimate Local Authority (the ultimate Client for each relevant project), undertaking extensive daily inspections of the building works.

As with other projects, a degree of non-compliant works occurred on each of the five school sites; with some sites experiencing a greater level of non-compliant works than others. In all cases I found that the site based personnel were very willing to seek to rectify the non-compliant works; albeit they were often prevented from doing so by managerial pressure from above.

The pressure from above often being so great that very capable, very principled personnel felt they were left with little choice other than to allow the presence of non-compliant works or risk losing their positions.

Both Main Contractors I worked with had extensive, third party certified, quality assurance policies and processes; and both Contractors had skilled and experienced Project and Construction Managers. If left to follow their own judgement I am confident the level of non-compliant works would have been reduced.

A top-down managerial commitment to producing quality workmanship (just as with the top-down approach to health and safety) has helped; and is required if instances of large scale defective works are to be avoided.

The balancing of the Cost, Time, Quality triangle requires a great deal of thought (by all parties) during the Tender and Pre-Contract periods of a project if quality (and other) problems are to be avoided during the construction phase.

  • 24th Mar 2017, at 06:50 AM
  • Adam Sharp

Leave a comment

Comment

21 March 2017 CIOB president Paul Nash: Industry must act on Edinburgh schools

21 March 2017 Offsite... it's just not building really is it?

06 March 2017 Construction must strive for offsite’s schedule certainty

03 March 2017 Procurement is key to a better industry

26 February 2017 Councils must take on more risk to increase housing

22 February 2017 Skills crisis: Facing up to the numbers

20 February 2017 A response to Sadiq Khan's Direct Vision Standard

14 February 2017 Housing White Paper: Why industry must play its part

14 February 2017 Chris Blythe: time to fix the leasehold rip-off

14 February 2017 Vox pop: The good and the bad in the Housing White Paper

10 February 2017 Housing White Paper fails to address community funding

09 February 2017 Bonfield review falls a few steps short

07 February 2017 Vox pop: What changes would you like to see in the light of the CITB review?

05 February 2017 Leader: We need to start linking tech to the bottom line

30 January 2017 Brexit puts our shortcomings in focus

29 January 2017 Chris Blythe: Avoid the snakes to continue industry's ascent

25 January 2017 Brexit - the implications for public sector procurement

12 January 2017 Changing the industry starts with offsite

05 January 2017 Vox pop: How will corporate activity pan out for construction this year?

02 January 2017 Leader: Here's to a healthier and more productive 2017