Me and my project: Benjamin Findlay MCIOB

The director at Quanstruct Consulting on Crossrail, studying for a Masters, CIOB activity and building for Google.

Ben Findlay

One of the projects that Quanstruct Consulting is currently involved in is the Crossrail South East Section in Abbey Wood, London (in conjunction with Balfour Beatty). I commercially manage the MEPH (mechanical, electrical, public health) and SISS (station information & surveillance systems) packages as well as acting as interim commercial manager.

During the past 15 months, I have had to overcome many complex procurement issues due to the multiple phased programme of works.

However, I’m used to managing tight deadlines: outside of my day job I am studying part time for a master’s degree in Construction Law & Dispute Resolution at King’s College London, am an active committee member of the CIOB Maidstone Hub and also a committee member of the CIArb South East Branch.

Due to the fast-paced environment and heavy procurement and subcontract burden the South East Section project brings, the commercial team is very busy managing contractors under the ICE NR12 contract conditions. Time is of the essence for cost reporting to the JV steering board.

I have managed to streamline the cost reporting process by creating a “one stop shop” spreadsheet that can be used at project and at client level, which captures all important cost associated items. This has been implemented by the JV members, and has helped saved a lot of time and clarified costs.

Findlay drew from his experience on the Google Data Centre in Finland (above) for his Crossrail project (top)

In meeting these challenging opportunities I’ve drawn on my experience  in Finland working as commercial manager on a logistically challenging appointment installing complex electrical infrastructure within Google Data Centres.

I had to set up a local business for them to trade and abide by local tax legislation, appoint a local accountant, open a Finnish bank account, procure local contractors and suppliers under Finnish contract conditions, procure UK-based contractors, suppliers and labour which included agreeing flight and accommodation costs for the project duration.

The cost reporting was undertaken in the UK head offices and in dual currency. I was on a plane over 60 times that year, flying to Helsinki followed by a two-hour drive, but to see the successful outcome of the project made it all worthwhile.

Leave a comment

On Site

11 May 2017 Me and my project: Benjamin Findlay MCIOB

11 May 2017 H&S - does your mask pass the face fit test?

10 May 2017 Plantworx Innovation Awards: Rise of the machines

09 May 2017 Factory visit: a board meeting in Northumberland

02 May 2017 How BIM helped refurb Lord's Media Centre

26 April 2017 New stand at Lord's set to wow crowds this summer

25 April 2017 The solution: Going round the bend in Slough

25 April 2017 The machine that could spell the end for bricklayers

11 April 2017 Solar gain and how to avoid it

06 April 2017 Don't leave occupational health in the dust

30 March 2017 Modular housing hits the heights in north London

27 March 2017 Project spotlight: Surrey's eyesore to eye candy

06 March 2017 Scheme trains prisoners in offsite housing

28 February 2017 ISG's ripping yarn in central London

22 February 2017 Project spotlight: How Reading's Thames Tower was made fit for 21st century

21 February 2017 Time to give inadequate footwear the boot

02 February 2017 Crossrail special: Grand central at Tottenham Court Road

01 February 2017 Crossrail special: A journey into the future

26 January 2017 Crossrail special: Station to station

24 January 2017 Project spotlight: UEA student accommodation