EoT cancels out certificate of non-completion

Theresa Mohammed and Zoeyah Shaheen describe a case in which the wording of the contract was critical in assessing whether liquidated damages were payable.

Construction contracts often include a provision that requires the contractor to pay liquidated damages to the employer as a remedy for contractor-caused delay beyond the stipulated date for sectional completion or completion of the whole project.

Simple liquidated damages provisions are based on a pre-estimate of the loss the employer would incur as a result of the contractor failing to meet the completion date. They are generally set as a fixed daily or weekly sum and may include sums for loss of rent, financing charges, and any costs associated with delayed completion that the employer anticipates will be incurred.

The standard form contracts, and in particular the JCT suite of contracts, requires certain notices to be served before the employer is able to start levying liquidated damages against payments otherwise due to the contractor or collect liquidated damages as a debt. If that contractual process is not followed, the damages cannot be levied.

Octoesse LLP engaged the contractor, Trak Special Projects Ltd, for the construction of residential and retail units in Long Acre, London WC2. The contract used for the project was the Standard Form JCT Intermediate Building Contract (IC 2011).

The initial date for completion, 22 September 2013, was extended to 29 September 2013 due to a delay in the commencement of the works; however, the works remained incomplete. On 3 October 2014, the contract administrator issued a certificate of non-completion and on 13 February 2015, the works were certified as practically complete.

On 3 July 2015, Trak submitted a claim for an 18-week extension of time. In response, the contract administrator granted Trak a nine-and-a-half week extension of time on 9 November 2015, which did not obviously cover the whole period of delay. No further certificate of non-completion was issued. On 4 May 2016, the final certificate was issued for payment and on 16 May 2016 Octoesse issued a pay less notice deducting liquidated damages of £89,250.

Trak began an adjudication claiming that further monies were due to them and the adjudicator found that Octoesse was not entitled to deduct liquidated damages, that the pay less notice was invalid and that Octoesse should pay Trak £59,991.83 plus interest and other sums.

Octoesse did not comply with the decision and applied for a declaration on the law in respect of clauses 2.22 and 2.23 of the contract. In her judgment on 15 December 2016, Mrs Justice Jefford held that the recoverability of the liquidated damages turned on the proper construction of clauses 2.22 and 2.23 of the contract:

“Clause 2.22. If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Architect/Contract administrator shall issue a certificate to that effect. If an extension of time is made after the issue of such certificate, the extension shall cancel that certificate and the Architect/Contract Administrator shall where necessary issue a further certificate.”

It was an express condition of Octoesse’s entitlement that it had given notice under clause 2.23.2 and that the contract administrator had issued a certificate pursuant to clause 2.22. Trak argued that this condition had not been met because the certificate of non-completion issued in October had been cancelled when a further extension of time had been granted in November 2015. Clause 2.22 required the issue of a further certificate to allow Octoesse to levy the liquidated damages.

Octoesse submitted that it was not necessary for the contract administrator to issue a further notice of non-completion because practical completion had already taken place prior to an extension of time being granted. This meant that Trak was fully aware of its potential liability for liquidated damages.

However, Justice Jefford held that Octoesse’s argument had failed to give effect to the mandatory requirement established by the word “shall” in Clause 2.22. Indeed, as the extension of time cancelled the previously issued certificate, absent such a certificate the requirements of the contract were not fulfilled and Octoesse was not entitled to deduct liquidated damages.

This case stresses the importance of the preconditions to the valid levy of liquidated damages and should certainly prompt employers and those acting as consultants to employers to make sure that if an extension of time is given that does not encompass the whole period of delay that a further certificate of non-completion is issued. To fail to do so removes the employer’s right to liquidated damages even when there is no defence to culpable contractor delay.

Theresa Mohammed is a partner and Zoeyah Shaheen a solicitor in contentious construction at Trowers & Hamlins

Leave a comment

Management

22 May 2017 Faith can move mountains, but not contracts

18 May 2017 In pictures: Ransomware explained

16 May 2017 Contracts, like climbing, require an escape route

14 May 2017 Apprenticeship levy: making the most of it

11 May 2017 Five ways to reduce bid costs

09 May 2017 How to create a workspace for everyone

04 May 2017 Balancing the risk and reward of innovation

04 May 2017 Apprenticeship levy and how to spend it

01 May 2017 Why construction is like doing the hokey-cokey

27 April 2017 How not to challenge an adjudication

18 April 2017 How can we overcome BIMwash?

18 April 2017 What's in store for NEC4?

11 April 2017 Preparing for Brexit - what you need to be doing

06 April 2017 Need to know: apprenticeship levy FAQ

06 April 2017 Adding social value, improving diversity

03 April 2017 SMEs get a better chance of chasing late payment

27 March 2017 Getting the measure of global standards

23 March 2017 EoT goes at the end of completion date, right?

16 March 2017 New school frameworks explained

14 March 2017 GMP leads to pain if you don't tread carefully